image

Project management glossary

Discover essential project management terminology in our glossary. Gain clarity on crucial concepts and boost your project management skills as you explore our detailed guide.
Project management glossary

A

Accept
A decision to take no action against a risk, typically when it falls below risk thresholds.
Acceptance criteria
Specific requirements that deliverables must meet to be formally accepted.
Acceptance test
A test run by end users to determine if a product meets their needs.
Accountability
The obligation to answer for results and take ownership of work.
Acquisition process
The process of obtaining personnel and resources necessary for project work.
Action item
A task or activity that must be completed.
Action item status
Tracks an action item’s progress from creation to closure.
Activity
The smallest unit of work in a project, requiring time, resources, and finances to complete.
Activity code
An alphanumeric value used to group and filter activities.
Activity duration
The length of time it takes to complete an activity.
Activity identifier
A unique alphanumeric value assigned to each activity.
Activity label
A short descriptor for an activity.
Activity list
A document listing all activities necessary to complete a project.
Activity network
A diagram showing the sequence and dependencies of project activities.
Activity-on-arrow (AOA)
A network diagram where arrows represent activities and nodes represent events or milestones.
Activity-on-node (AON)
A network diagram where nodes represent activities and arrows show logical relationships.
Actual cost
The total cost incurred for work done in a given period.
Actual duration
The length of time taken to complete an activity.
Actual effort
The amount of labour performed to complete an activity, expressed in person-hours or similar units.
Actual expenditure
The sum of costs paid from a budget.
Actual finish
The date on which an activity was completed.
Actual progress
A measure of work completed on a project, usually stated as a percentage.
Actual start
The date on which an activity was started.
Adaptive project framework (APF)
An approach that accepts changing requirements and allows projects to be affected by external business environments.
Administrative closure
The set of formal requirements fulfilled to end a project.
Aggregate planning
A strategy using demand forecasts to manage scheduling and planning for project activities.
Agile
A family of iterative development approaches aimed at meeting changing customer requirements through sprints.
Agile project management
An approach focusing on teamwork, collaboration, and stakeholder involvement, using iterative development methods.
Agile software development
A development approach originating from the Agile Manifesto, emphasizing meeting changing requirements through collaborative development.
Allocation
The assigning of resources for scheduled activities in the most efficient way possible.
Alternative analysis
The evaluation of possible courses of action for project work.
Analogous estimating
An estimation technique using historical project data to prepare time and cost estimates.
Analytical estimating
A technique that computes total project time and cost estimates by preparing estimates for each project activity.
Application area
The specific project category of which the project is a part.
Apportioned effort
Project work associated with components of a work breakdown structure and performed in proportion with discrete effort.
Approach analysis
An analysis used to examine various methods by which project goals may be achieved.
Arrow diagramming method (ADM)
A method of constructing a network diagram using arrows to represent activities and nodes to represent events or milestones.
Artifact
Items that support software development, including project plans and items used in actual development.
As late as possible (ALAP)
An activity for which the early start date is set as late as possible without delaying successor activities.
As soon as possible (ASAP)
An activity for which the early start date is set to be as soon as possible.
Assignment contouring
The process of assigning people to project work for changing numbers of hours per day as the project progresses.
Assumption
Factors deemed to be true during project planning, though proof of their validity is not available.
Authorization
The power to make decisions granted by management.
Authorized work
Work approved by management or others in authority.
Avoid
A response to a negative risk that seeks to ensure the risk does not occur or to protect project objectives from its impact.

B

Backward pass
A technique to calculate late-start and finish dates for project activities by working backwards from the project end date.
Balance
A phase in the portfolio life cycle involving balancing portfolio components based on risk, costs, and resource use.
Balanced matrix
An organizational structure where functions and projects have the same priority.
Balanced scorecard
A tool used to assess whether an organisation’s activities align with its vision and objectives.
Bar chart
A diagrammed calendar schedule of project activities’ start and end dates in logical order.
Base date
A reference date used as the start of a project calendar.
Baseline
The approved costs and schedules at the start of the project, used as a basis for monitoring and evaluating performance.
Baseline cost
The amount of money a project or activity was intended to cost when the project plan was baselined.
Baseline date
The original planned start and finish dates for a project or activity when the schedule was baselined.
Baseline plan
The fixed project plan used as the standard for measuring performance.
Baseline schedule
The fixed project schedule used as the standard for measuring performance.
Benchmarking
A review of what other organisations are doing in the same area.
Benefit
A positive and measurable impact of change.
Benefits framework
An outline of expected project benefits, affected business operations, and performance measures.
Benefits management
The identification, definition, planning, tracking, and realisation of benefits.
Benefits management plan
A plan specifying responsibility for achieving benefits and how they will be measured and managed.
Benefits profile
A representation of when benefits are planned to be realised.
Benefits realisation
The practice of ensuring benefits are derived from outputs and outcomes.
Benefits realisation review
A review undertaken after project deliverables have been in operation to establish if benefits have been realised.
Bid
A tender, quotation, or offer to enter into a contract.
Bid analysis
An analysis of bids or tenders.
Bid list
A list of contractors or suppliers invited to submit bids for goods or services.
Bidding
The process of preparing and submitting a bid or tender.
Blueprint
A document defining what a programme is designed to achieve in terms of business and operational vision.
Board
A body providing sponsorship to a project, programme, or portfolio, representing financial, provider, and user interests.
Bottom-up estimating
A technique that computes total project time and cost estimates by preparing estimates for each activity and adding them together.
Budget
The sum of money allocated for a project or a comprehensive list of revenues and expenses.
Budget at completion (BAC)
The sum total of the time-phased budgets.
Budget cost
The cost anticipated at the start of a project.
Budget element
Resources needed to do the work, typically assigned to a work package.
Budget estimate
An approximate estimate prepared in early project stages to establish financial viability or secure resources.
Budgeted cost of work performed (BCWP)
The planned cost of work completed to date, also known as ‘earned value’.
Budgeted cost of work scheduled (BCWS)
The planned cost of work scheduled to be performed in a period of time.
Budgeting
Time-phased financial requirements.
Budgeting and cost control
The estimation of costs, setting of an agreed budget, and management of actual and forecast costs against that budget.
Buffer
A term used in critical chain for the centralised management of schedule contingencies.
Build (stage)
A stage within the implementation phase where project deliverables are built or constructed.
Build, own, operate, transfer (BOOT)
A situation where a private operator builds, owns, operates, and then transfers a facility to another party after a specific period.
Burn down chart
A graph showing the relationship between tasks to be completed and the remaining time.
Business analysis
The practice of identifying and solving business problems.
Business case
Documentation of potential outcomes of a new project, including benefits, costs, and effects.
Business change manager
The role responsible for benefits management from identification through to realisation.
Business imperative
An issue, situation, or circumstance with potential to affect a business.
Business model
The system by which an organization’s profitable activities are planned, structured, and executed.
Business operations
The ensemble of activities or processes through which a company uses its assets to create value for customers.
Business process
A system of activities by which a business creates a specific result for its customers.
Business Process Modelling (BPM)
The representation, analysis, and evaluation of business processes to improve them.
Business readiness
A continuous concern through a project or programme that seeks to understand attitudes to change and barriers.
Business requirements
The conditions a product must satisfy to effectively serve its purpose within a business.
Business risk assessment
The assessment of risk to business objectives rather than risk to achieving project objectives.
Business value
The sum of positive effects a project has on the business.
Business-as-usual
An organisation’s normal day-to-day operations.

C

Calendar unit
The smallest unit of time by which project activity durations are measured.
Capability
A project outcome that enables a benefit to be achieved, or having necessary attributes to perform or accomplish.
Capability Maturity Model (CMM)
A model used to assess the maturity of business process capabilities.
CAPEX
Capital expenditure, the money a company spends to acquire or upgrade fixed physical assets.
Case study
Extensive and in-depth formal research into an area of a company, situation, or event.
Certified Associate in Project Management (CAPM)
An entry-level certification for project managers offered by the Project Management Institute.
Champion
An informal role where a person makes project success a personal responsibility.
Change control
The process of identifying, evaluating, approving, and implementing changes to a project.
Change control board
An appointed group of stakeholders who evaluate proposed changes and decide when and whether to make them.
Change control system/process
The process by which changes to the project are evaluated, implemented, and documented.
Change freeze
The point at which scope changes to a project are no longer permissible.
Change management plan
A plan detailing the change control process.
Change request
A formal document submitted to request changes to the finalised project management plan.
Client/Customer
The people who will directly benefit from a project.
Closing phase
The final phase of the project life cycle where all aspects are officially completed and closed.
Code of accounts
An alphanumeric system used to assign unique identifiers to all work breakdown structure components.
Collaborative negotiation
Negotiations where all parties obtain at least some of what they want.
Communications log
A document used to track all project-related communications.
Communications management plan
A plan stating who will send and receive project information, what details are communicated, and when.
Communities of practice
Groups of people who share an area of interest within project management and meet regularly to share knowledge.
Competence
The ability and knowledge required to perform tasks associated with a specific role.
Competence framework
The set of competence expectations used to assess a person’s suitability for a specific role.
Concept
The beginning phase of the project life cycle where the team presents opportunities or problems and examines project feasibility.
Conceptual project planning
Developing documentation from which a project’s organization and control system will originate.
Concurrent engineering
A product development approach where design and development are carried out simultaneously.
Configuration
Shaping a product’s functions and characteristics to make it suitable for customer use.
Configuration management
Ensuring that the product of a project meets all necessary specifications and stipulations.
Consensus
A decision agreed upon by all members of a group.
Constraint
A limitation on a project, such as financial, time, or resource availability constraints.
Constructability
A concept used in complex projects to assess the entire construction process before beginning construction.
Construction
The process of building infrastructure, typically supervised by engineers and architects and managed by a project manager.
Consumable resource
A non-renewable resource that cannot be used once consumed.
Contingency plan
An alternative course of action planned in anticipation of specific risks.
Contingency reserve
An allocation of time or money set aside for known possibilities that could delay a project or make it more expensive.
Contract administration
The process of managing a relationship with a contracting party.
Contract closeout
The process of determining whether contract terms were completed successfully and settling any remaining terms.
Control account
A work breakdown structure tool that allows aggregation of costs for work packages as part of earned value management calculations.
Control chart
A chart that compares process results with historical averages and control limits to show whether a process meets expectations.
Core process
A process that follows an established order and is central to the performance of the system or project of which it is part.
Corrective action
A step taken to bring work back into alignment with performance expectations after it has failed to meet them.
Cost baseline
The sum of work package estimates, contingency reserve, and other associated costs by which project performance is assessed.
Cost benefit analysis
An analysis used to weigh project costs against anticipated tangible benefits.
Cost engineering
The application of scientific and engineering principles to aspects of cost management.
Cost management plan
A plan detailing how project costs will be planned, funded, and controlled.
Cost of quality
The cost associated with ensuring project quality.
Cost overrun
When unexpected costs cause a project’s actual cost to exceed the budget.
Cost performance index
A measure of cost efficiency calculated as the ratio of earned value to actual cost.
Cost Plus Fixed Fee Contract (CPFC)
A contract where the seller is reimbursed for costs and paid a predetermined fixed fee.
Cost Plus Incentive Fee Contract (CPIF)
A contract where the seller is reimbursed for costs and paid an additional fee if they meet specified performance criteria.
Cost Plus Percentage Of Cost Contract (CPPC)
A contract where the seller is reimbursed for costs and paid an additional amount equal to a percentage of costs incurred.
Cost reimbursable contract
A contract where a seller is reimbursed for costs and paid an additional sum as profit.
Cost variance
The difference between earned value and actual cost.
Cost/schedule impact analysis
An analysis determining the effects of a change on a project’s cost or schedule.
Crashing
A schedule compression technique used to speed up project work by increasing resources on critical path activities.
Critical Chain Project Management (CCPM)
An approach emphasizing resources needed to complete project activities over activity order and durations set in a schedule.
Critical Incident Stress Debriefing (CISD)
A psycho-educational exercise for small groups who have experienced a traumatic event.
Critical path
The sequence of activities through a project network from start to finish, the sum of whose durations determines the overall project duration.
Critical path activity
A scheduled activity that is part of a project’s critical path.
Critical path method
A technique used to estimate the shortest project duration and determine float for non-critical path activities.
Critical success factor
An aspect of a project crucial to its success.
Criticality index
A percentage representing how frequently an activity is on the critical path in project simulations.
Current finish date
The most up-to-date estimate of when an activity will finish.
Current start date
The most up-to-date estimate of when an activity will start.
Cut-off date
The end date of a reporting period.

D

Data date
A point at which a project’s status is measured and documented.
Decision bias
Psychological biases affecting individuals and groups when making risk-based decisions.
Decision gate
A point between phases used to review and confirm work viability in line with the business case.
Decision tree analysis
A diagrammatic technique used to illustrate a chain of decisions and examine implications of multiple outcomes.
Decomposition
The hierarchical breaking down of project deliverables into smaller, more manageable components.
Defect repair
An action taken to remedy a nonfunctional product or one that doesn’t match expectations.
Define
The phase of a portfolio life cycle where projects, programmes, and changes required to meet strategic objectives are identified and evaluated.
Defined
The third level of a typical maturity model where processes are documented and standardised.
Definition
The second phase of a project life cycle where requirements are refined and ways of achieving them are identified.
Deliverable
A final product or product component that must be provided to a client or stakeholder according to contractual stipulations.
Delphi technique
An estimation method based on expert consensus through rounds of individual estimates and group reviews.
Dependency
A logical relationship between project activities in a network diagram that determines when a dependent activity may begin.
Design (stage)
A stage within the implementation phase where the design of project deliverables is finalised.
Design authority
The person or organisation with overall design responsibility for project products.
Detailed design
The in-depth design of the chosen solution, ready for full implementation.
Deterministic estimate
A predetermined estimate with no possibility of an alternative outcome.
Development
The working up of a preferred solution to an optimised solution during project phases.
Deviations
Departure from the established plan or requirements.
Direct labour
Labour specifically identified with a particular activity, incurred for the exclusive benefit of the project.
Disbenefit
A consequence of change perceived as negative by one or more stakeholders.
Do nothing option
The result or consequence of not proceeding with the project or programme.
Drawdown
The removal of funds from an agreed source resulting in a reduction of available funds.
Dummy activity
In activity-on-arrow diagrams, a logical link that may require time but no other resource.
Duration
The length of time needed to complete the project or an activity.
Duration compression
The shortening of a project schedule without reducing scope, often resulting in increased cost.
Dynamic Systems Development Method (DSDM)
An agile development method for developing business solutions within tight timeframes.

E

Earliest finish date
The earliest possible date by which an activity can finish within logical and imposed constraints.
Earliest start date
The earliest possible date when an activity can start within logical and imposed constraints.
Earned hours
The time credited as a result of completing a given activity or group of activities.
Earned value
A measure of progress expressing costs committed and work achieved in the same units.
Earned value analysis
An analysis of project progress comparing actual money and hours spent to the value of work achieved.
Earned value management
A project control process based on a structured approach to planning, cost collection, and performance measurement.
Effort
The number of labour units necessary to complete work, usually expressed in labour hours, days, or weeks.
Effort-driven activity
An activity whose duration is governed by resource usage and availability.
Effort estimate
A calculated approximation of the effort needed to complete an activity.
Effort management
The most efficient allocation of time and resources to project activities.
EFQM Excellence Model
A model for diagnosing organisational excellence.
Elapsed time
The total number of calendar days needed to complete an activity.
Emergent change
Unplanned change managed by an organisation through incremental, iterative, or evolutionary approaches.
End activity
An activity with no logical successors.
End user
The person or organisation that will use the facility produced by the project.
Enhance
A response to an opportunity that increases its probability, impact, or both.
Enterprise project management office
An organisation responsible for the governance infrastructure of project, programme, and portfolio management.
Environment
The societal and/or organisational setting of a project, programme, or portfolio.
Escalate
The process by which issues are drawn to the attention of a higher level of management.
Estimate
A forecast of the probable time or cost of completing work.
Estimate At Completion (EAC)
A value expressed in money and/or hours representing the projected final costs of work when completed.
Estimated Cost to Complete (ECC)
The value expressed in money or hours representing the cost of work required to complete an activity.
Estimating
The use of tools and techniques to produce forecasts of the probable time or cost of completing work.
Estimating funnel
A representation of increasing levels of estimating accuracy achieved through project phases.
Ethical procurement
Procurement in accordance with established ethics or moral values.
Ethics frameworks
Recognised standards of conduct and behaviour within the project, programme, and portfolio profession.
Event-driven
Describing an action prompted by the occurrence of an event.
Event chain diagram
A visual representation of a schedule network based on event chain methodology.
Event chain methodology
A schedule network analysis method that enables uncertainty modelling.
Exception management
An approach focusing on instances where planned and actual results are significantly different.
Exceptions
Occurrences causing deviation from a plan, such as issues, change requests, and risks.
Expected monetary value
The product of an event’s probability of occurrence and the financial gain or loss that will result.
Expediting
The facilitation and acceleration of progress by removing obstacles.
Expended hours
The hours spent to achieve an activity or group of activities.
Expenditure
A charge against available funds, evidenced by a voucher, claim, or another document.
Exploit
A response to an opportunity that maximises both its probability and impact.
Extended life cycle
A life cycle approach adding an adoption phase to facilitate cooperation between change and business-as-usual teams.
External constraint
A constraint from outside the project.
External environment
The environment external to the organisation carrying out the project.
External suppliers
Suppliers external to the organisation carrying out the project.

F

Facilitation
An approach to working with groups collaboratively to create energy and solve problems.
Facility
The final result, outcome, or deliverable of the project.
Factors
Situations that affect or influence outcomes.
Fast tracking
A schedule compression technique where critical path activities are performed concurrently instead of consecutively.
Feasibility study
An evaluation of how likely a project is to be completed effectively.
Final account
The account that finally closes a purchase order or contract.
Financial management
The process of estimating and justifying costs to secure funds, control expenditure, and evaluate outcomes.
Financing and funding
The means by which capital for a project is secured and made available.
Finish-to-finish
A dependency indicating that one activity cannot finish until another activity has finished.
Finish-to-finish lag
The minimum time that must pass between the finish of one activity and the finish of its successor(s).
Finish-to-start
A dependency indicating that one activity cannot start until another activity has finished.
Finish-to-start lag
The minimum time that must pass between the finish of one activity and the start of its successor(s).
Fitness for purpose
The degree to which project management processes and deliverables satisfy stakeholder needs.
Fixed date
A calendar date associated with a schedule that cannot be moved or changed.
Fixed or non-recurring cost
A cost not influenced by volume of business or quantity.
Fixed price contract
A contract based on firm legal commitments to complete required work.
Float
The flexibility with which an activity may be rescheduled.
Flow diagram
A graphic representation of workflow and logical sequence of work elements.
Force-field analysis
A technique to identify pressures promoting or resisting change.
Forecast
A prediction of a defined future state, typically related to project duration and cost.
Forecast costs
A projection of future costs that the project will incur.
Forecast final cost
A projection of total costs at project completion.
Forecast outturn cost
The cost of actual expenditure, accruals, and estimated costs to complete the work.
Form of contract
The type of contract to be used, often a standard form relevant to the business or industry sector.
Forward pass
A technique to calculate earliest start and finish dates for activities.
Free float
Spare time at the end of an activity that can be used without delaying its successor.
Function
A specialist department providing dedicated services.
Functional analysis
Identification and analysis of functional attributes of different solutions.
Functional Analysis and System Technique (FAST)
An evolution of the value analysis process linking simply expressed functions to describe complex systems.
Functional departments
Specialist departments providing dedicated services.
Functional manager
The person responsible for business and technical management of a functional group.
Functional organisation
A management structure where specific functions are grouped into specialist departments.
Functional requirements
The working characteristics of a product based on end-user needs.
Functional specification
A document specifying required functions of a system and applicable constraints.
Funding
The means by which money for a project is secured and made available.
Funding profile
An estimate of funding requirements over time.

G

Gantt chart
A graphical representation of project activities against time.
Gate
A point between phases where a go/no go decision is made about remaining work.
Gate review
A formal point where a project’s worth, progress, cost, and execution plan are reviewed.
Go/No go
A form of control where a decision is made whether to continue work.
Goal
A one-sentence definition of what will be accomplished, incorporating an event signifying completion.
Governance
The framework of authority and accountability that defines and controls project outputs, outcomes, and benefits.
Governance board
A body providing sponsorship to a project, representing financial, provider, and user interests.
Guarantees
Legally enforceable assurance of performance of a contract.

H

Hammock
A summary task linked to a group of activities, with duration determined by the total elapsed duration of linked activities.
Handover
The point where deliverables are commissioned and given to the permanent organisation.
Health and safety management
The process of identifying and minimising threats to workers throughout the project life cycle.
Health and safety plan
A plan identifying health and safety strategies and procedures for a project.
Health and safety risk assessment
A legislative requirement for all employers and self-employed individuals.
Health, safety and environmental management
The process of applying standards to minimise accidents, injuries, or environmental damage.
Hierarchical coding structure
A multi-level tree structure coding system where every code except those at the top has a parent code.
High-level requirements
A high-level statement of project needs.
Host organisation
The organisation providing strategic direction and primary investment for a project.
Hybrid life cycle
An approach combining linear and iterative life cycles for different phases or activities.
Hypercritical activities
Activities on the critical path with negative float.

I

Idea development
Developing evaluated opportunities to understand benefits and costs.
Idea evaluation
Ranking identified opportunities according to their appropriateness.
Impact
The assessment of a risk’s effect on an objective if it occurs.
Impact analysis
An assessment of the merits of a course of action or potential impact of a requested change.
Implementation
The third phase of the project life cycle where the project management plan is executed, monitored, and controlled.
Imposed finish
A finish date imposed on an activity by external circumstances or constraints.
Imposed start
A start date imposed on an activity by external circumstances or constraints.
In progress activity
An activity that has been started but not yet completed.
Influence diagram
A pictorial representation of how variables affect one another.
Influencing
The act of affecting the behaviours and actions of others.
Information management
The collection, storage, curation, dissemination, archiving, and destruction of information.
Infrastructure
Support for projects, programmes, and portfolios, focal point for their development and maintenance.
Initial
The first level of a typical maturity model where processes are typically ad hoc and occasionally chaotic.
Initiation
The process of committing to begin a project, establishing clear reference terms and management structure.
Integrated assurance
The coordination of assurance activities where there are multiple assurance providers.
Integrated baseline review
A review held following the establishment of the initial baseline.
Integrated planning
The application of management processes bringing together planning of benefits, success criteria, scope, quality, time, resources, cost, risk, communications, etc.
Integration
The process of bringing people, activities, and other things together to perform effectively.
Integrative management
Management processes that bring together planning of various project aspects.
Interdependencies
The management of dependencies between projects and business-as-usual activities.
Interface management
The management of relationships between different departments or organisations on a project.
Interface management plan
A plan identifying and showing how to manage internal and external project interfaces.
Internal environment
The environment internal to the organisation carrying out the project.
Internal Rate of Return (IRR)
The discount rate that makes the net present value of all cash flows equal to zero.
Interrelationship
The relationship between activities managed by a team or individual.
Investment
The outlay of money or time for income, profit, or other benefit.
Investment appraisal
Analysis considering investment profitability over an asset’s life alongside affordability and strategic fit.
Investment decision
The decision justifying investment in a project, based on robust investment appraisal.
Invitation To Tender (ITT)
An invitation to a supplier to bid for the supply of goods or services.
Island of stability
A review point at the end of a programme tranche when progress is reviewed and the next tranche planned.
Issue
A problem breaching or about to breach delegated tolerances, requiring sponsor support to resolve.
Issue log
A log of all issues raised during a project, showing details, evaluation, decisions, and current status.
Issue management
The process of identifying and addressing issues to remove threats they pose.
Issue register
A log of all issues raised during a project.

J

Joint Venture (JV)
A joint ownership of a firm by two or more parties engaged in a particular venture.
Just In Time (JIT)
A philosophy where goods, services, or actions are provided on demand without waiting or storage.

K

Key events
Major events critical to project execution.
Key events schedule
A schedule of major events critical to project execution.
Key milestone
A milestone critical to project success.
Key Performance Indicators (KPI)
Measures of success used throughout the project to ensure progress towards success.
Knowledge management
The discipline concerned with how organisations create and use knowledge to improve outcomes.

L

Lag
The minimum necessary lapse of time between the finish of one activity and the start of another.
Latest finish date
The latest possible date by which an activity must finish without affecting total project duration.
Latest start date
The latest possible date by which an activity must start without affecting total project duration.
Lead
A negative lag, by definition an illogical condition.
Leadership
The ability to establish vision and direction, influence and align others towards a common purpose, and empower and inspire people.
Lean
An approach concerned with identifying principles by which environments can become more responsive, flexible, productive, reliable, and cost-effective.
Lessons learned
Documented experiences used to improve future management of projects, programmes, and portfolios.
Letter of intent
A letter indicating intent to sign a contract, usually to allow work to commence prior to signing.
Level one plan
The master plan for the project, with level two and three plans providing successively more detail.
Levelling
The process of resolving resource conflicts by delaying tasks.
Life cycle
A framework comprising distinct high-level stages required to transform an idea into reality.
Life cycle cost
The cumulative cost of a project over its whole life cycle.
Line-of-balance
A scheduling technique for repetitive products showing how resource teams move from product to product.
Linear life cycle
A life cycle aiming to complete a project within a single pass through distinct, sequential phases.
Liquidated damages
The liability in a contract to pay a specified sum for a breach of contract.
Logic
The sequence and interdependencies of activities in a project schedule.
Logic diagram
A graphical representation of the sequential relationship between project activities.
Logical dependency
A dependency based on the relationship between two activities or between an activity and a milestone.

M

Make or buy decision
The decision to make a deliverable internally or buy a finished deliverable from a supplier.
Managed
The fourth level of a typical capability maturity model where metrics are gathered on process performance.
Management by exception
Management focused on problem or critical areas only.
Management development
All aspects of staff planning, recruitment, development, training, and assessment.
Management plan
A plan setting out how an aspect of a project, programme, or portfolio will be delivered.
Management reserve
A sum of money to cover the cost impact of unidentified risks and some very low-probability, high-impact risks.
Marketing
Anticipating user demands and identifying and satisfying their needs.
Master schedule
A high-level summary project schedule identifying major activities and milestones.
Material
Property incorporated into, attached to, or consumed in the performance of a contract.
Material take-off
A list of materials required to build an item, derived from a drawing.
Matrix organisation
An organisational structure where project managers and functional managers share responsibility for assigning priorities and directing work.
Maturity
The sophistication and experience of an organisation in managing projects.
Maturity model
An approach to understand current capabilities and identify a structured path to increase success predictability.
Mechanical completion
The point at which a facility is fully installed and components have been inspected and tested.
Mediation
An attempt to settle a legal dispute through active participation of a third party.
Method
A consistent framework within which project management is performed.
Method statement
A plan detailing how a piece of work is to be carried out.
Methods and procedures
Standard practices used for managing projects throughout a life cycle.
Milestone
A key event selected for its importance in the schedule, often associated with tangible acceptance of deliverables.
Milestone plan
A plan containing milestones that highlight key points of the project.
Milestone schedule
A schedule that identifies the major milestones.
Minimum viable product
A product with just enough features to satisfy early users and provide feedback for future development.
Mission statement
A brief summary that sums up the background, purpose, and benefits of the project.
Mobilisation
Ensures that the project has appropriate organisational and technical infrastructures and mechanisms for putting resources in place.
Model
A way of looking at reality to abstract and simplify it for understanding in a particular context.
Modelling
The process of creating and using a device that duplicates physical or operational aspects of a deliverable.
Monitoring
Recording, analysing, and reporting project performance compared to the plan to identify and report deviations.
Monte Carlo simulation
A technique used to estimate overall risk by predicting the combined effect of estimating uncertainty and specific risk events.

N

Near-critical activity
An activity with low total float that may become critical under adverse conditions.
Need, problem or opportunity
The underlying reason for undertaking a project.
Negotiated contract cost
The estimated cost negotiated in a cost-plus fixed fee contract or the negotiated contract target cost.
Negotiation
A discussion between two or more parties aimed at reaching agreement.
Net Present Value (NPV)
The difference between the present value of cash inflows and outflows over a period of time.
Network analysis
Collective term for different ways of analysing a network diagram.
Network diagram
A model of activities and their dependencies used in scheduling.
Network logic
The collection of activity dependencies that show logical relationships between activities.
Non-recurring costs
Expenditures against specific activities expected to occur only once on a given project.
Not earlier than
A restriction indicating an activity may not start or end earlier than a specified date.
Not later than
A restriction indicating an activity may not start or end later than a specified date.

O

Objectives
Predetermined results towards which effort is directed.
Operational life
Part of an extended life cycle when deliverables are operated and maintained.
Operations management
The management of activities that create core services or products provided by an organisation.
Operations phase
The period during which the completed deliverable is used and maintained for its intended purpose.
Opportunity
A positive risk event that, if it occurs, will have a beneficial effect on objectives.
Optimising
The fifth level of a typical maturity model where continuous process improvement is enabled by quantitative feedback.
Optioneering
An approach to exploring multiple options to optimally satisfy stakeholders’ needs.
Order of magnitude estimate
An estimate to give a very approximate indication of likely outturn costs.
Organisation
The management structure applicable to the project and the organisational environment in which it operates.
Organisation design
The design of the most appropriate organisation for a project.
Organisation structure
The organisational environment defining reporting and decision-making hierarchy.
Organisational Breakdown Structure (OBS)
A hierarchical way to divide the organisation into management levels and groups for planning and control purposes.
Organisational culture
The unwritten rules influencing individual and group behaviour and attitudes.
Organisational roles
Roles performed by individuals or groups in a project.
Original budget
The initial budget established at or near the time a contract was signed or a project authorised.
Original duration
The duration of activities or groups of activities as recorded in the baseline schedule.
Other Direct Costs (ODC)
Accounting elements that can be isolated to specific activities, other than labour and material.
Outcome
The changed circumstances or behaviour resulting from the use of an output.
Output
The tangible or intangible product typically delivered by a project.
Outturn cost
The expected final cost of a project.
Overhead
Costs incurred in business operation that cannot be directly related to individual products or services.
Overrun
Costs incurred in excess of the contract target costs or estimated costs.
Owner
The person or organisation for which the project is ultimately undertaken and who will benefit from the facility in the long term.

P

P3 assurance
The process of providing confidence to stakeholders that projects, programmes, and portfolios will achieve their objectives.
P3 management team
A collective term for those involved in the sponsorship and day-to-day management of a project, programme, or portfolio.
P3 management
The collective term for project, programme, and portfolio management.
Parallel activities
Two or more activities that can be done at the same time.
Parallel life cycle
A life cycle where phases are conducted in parallel.
Parametric estimating
An estimating technique using statistical relationships between historic data and other variables.
Pareto diagram
A histogram ordered by frequency of occurrence showing how many results were generated by each identified cause.
Partnering
An arrangement between organisations to manage a contract cooperatively.
Payback
An investment appraisal technique.
Percent complete
A measure of the completion status of a partially completed activity.
Performance
The term used to describe the quality of delivery and deliverables of the project.
Performance management
Techniques used in managing individual and team performance.
Performance measurement techniques
Methods used to estimate earned value.
PESTLE
A technique for analysing project context by considering political, economic, sociological, technical, legal, and environmental factors.
Phase
The major subdivision of a life cycle.
Phase reviews
A review that takes place at the end of a life cycle phase.
Physical models
A representation of the three-dimensional, solid aspects of a deliverable.
Physical percent complete
The percentage of work content of an activity achieved.
Physical performance
Actual performance of work that can be measured.
Pilot
A form of testing a new development and its implementation prior to committing to full release.
Plan
An intended future course of action.
Planned activity
An activity not yet started.
Planned cost
The authorised budget assigned to scheduled work to be completed.
Planned value
The cost profile of a resource-optimised schedule used as the baseline to monitor actual spend and earned value.
Planning
Determines what is to be delivered, how much it will cost, when it will be delivered, how it will be delivered, and who will carry it out.
Portfolio
A collection of projects and/or programmes used to structure and manage investments at an organisational or functional level.
Portfolio management
The selection, prioritisation, and control of an organisation’s projects and programmes in line with strategic objectives and capacity to deliver.
Portfolio prioritisation process
The evaluation and prioritisation of projects within a portfolio.
Post-project review
A review undertaken after project deliverables have been handed over to produce lessons learned.
PRAM
An abbreviation of the APM Risk Management SIG’s publication Project Risk Analysis and Management Guide.
Precedence diagram method
A method of representing projects as networks, with activities represented by nodes and relationships by arrows.
Precedence network
A model of activities and their dependencies used in scheduling.
Pre-commissioning
Work carried out prior to commissioning to demonstrate it may be safely undertaken.
Predecessor
An activity that must be completed before a specified activity can begin.
Predecessor activity
An activity that logically precedes the current activity.
Prime or lead contractor
A main supplier responsible for much or all of the work on a contract.
PRINCE2™
A project management methodology (PRojects IN Controlled Environments).
Prioritise
The phase of a portfolio life cycle where priorities are set by strategic objective, return on investment, or another chosen metric.
Probabilistic network
A network containing alternative paths with associated probabilities.
Probability
The likelihood of a risk occurring.
Problem
Concerns that the project manager deals with on a day-to-day basis.
Procedures
Individual aspects of project management practice forming an integral part of a method.
Procedures manual
A book of reference describing standard project procedures.
Procurement
The process of acquiring products and services from an external provider.
Procurement strategy
The high-level approach for securing goods and services from external suppliers.
Product
A tangible or intangible component of a project’s output.
Product Breakdown Structure (PBS)
A hierarchy of deliverables required to be produced on the project.
Product description
The description of the purpose, form, and components of a product.
Product flow diagram
A diagram representing how products are produced by identifying their derivation and dependencies.
Product life cycle
A life cycle approach adding operation and termination phases to reflect the whole life of an asset.
Productivity factor
The ratio of earned hours against expended hours.
Professionalism
The application of expert knowledge within a specific field and acceptance of related standards.
Profile of expenditure
A project’s budget phased over time to allow cash flow forecasting.
Program evaluation and review technique
A network analysis technique calculating standard deviations for the schedule based on three-point estimates of activity durations.
Programme
A unique, transient strategic endeavour undertaken to achieve beneficial change incorporating related projects and business-as-usual activities.
Programme benefits review
A review to assess if targets have been reached and measure performance levels in resulting business operations.
Programme brief
A description of the capability that the organisation seeks from changes to its business and/or operations.
Programme director
The senior manager responsible for the overall success of the programme.
Programme directorate
A committee that directs the programme when there is no individual to direct it.
Programme management
The coordinated management of projects and business-as-usual activities to achieve beneficial change.
Programme manager
The individual responsible for managing a programme.
Programme mandate
What the programme is intended to deliver in terms of new services and/or operational capability.
Programme support office
A group giving administrative support to the programme manager and executive.
Progress
The partial completion of a project, or a measure of the same.
Progress payments
Payments made to a contractor during the life of a fixed price contract based on an agreed formula.
Progress report
A regular report summarising project progress including key events, milestones, costs, and other issues.
Project
A unique, transient endeavour undertaken to bring about change and achieve planned objectives.
Project appraisal
The discipline of calculating the viability of a project.
Project assurance
Independent monitoring and reporting of the project’s performance and deliverables.
Project-based working
A collective term for project, programme, and portfolio management.
Project board
A group providing high-level direction to the project.
Project brief
The document produced during a project’s concept phase outlining requirements.
Project budget
The sum of money allocated for a project.
Project calendar
A calendar listing time intervals in which activities or resources can or cannot be scheduled.
Project charter
A document setting out working relationships and agreed behaviours within a project team.
Project closure
The formal end point of a project.
Project context
The environment within which a project is undertaken.
Project director
The manager of a very large project or person at board level responsible for project management.
Project environment
The societal and/or organisational setting of a project.
Project evaluation review
A documented review of project performance produced at predefined points.
Project file
A file containing overall project plans and important documents.
Project financing and funding
The means by which capital for a project is secured and made available.
Project initiation
The process of committing to begin a project.
Project Initiation Document (PID)
A document approved by the project board defining the project’s terms of reference.
Project life cycle cost
The cumulative cost of a project over its whole life cycle.
Project management
The application of processes, methods, knowledge, skills, and experience to achieve specific objectives for change.
Project Management Information System (PMIS)
The systems, activities, and data allowing information flow in a project.
Project management maturity
A model describing evolutionary levels of an organisation’s project management processes.
Project Management Office (PMO)
An organisational structure providing support for projects, programmes, and/or portfolios.
Project Management Plan (PMP)
The output of integrated planning for a project or programme.
Project management processes
The generic processes applied to each phase of the project life cycle.
Project management software
Computer application software designed to help with planning and controlling projects.
Project management team
Members of the project team directly involved in its management.
Project manager
The individual responsible for the successful delivery of the project.
Project mandate
The initial terms of reference for the project.
Project master schedule
A high-level summary project schedule.
Project objectives
Things to be achieved by the project, usually including technical, time, cost, and quality objectives.
Project office
An entity serving the organisation’s project management needs.
Project organisation
Provides maximum authority to the project manager and integration of functional capabilities within projects.
Project plan
See Project management plan.
Project planning
The development and maintenance of a project plan.
Project portfolio
See Portfolio.
Project procedures manual
See Procedures manual.
Project professional
A term describing people in roles associated with managing projects, programmes, or portfolios.
Project progress report
See Progress report.
Project quality management
See Quality management.
Project risk
The exposure of stakeholders to the consequences of variation in outcome.
Project risk management
A structured process allowing individual risk events and overall project risk to be understood and managed proactively.
Project roles and responsibilities
The roles and responsibilities of those involved in the project.
Project schedule
The tool communicating what work needs to be performed, which resources will perform it, and the timeframes for performance.
Project scope management
See Scope management.
Project sponsor
The individual ultimately responsible for the project.
Project start-up
The creation of the project team and making it effective.
Project status report
A report on the status of accomplishments and variances to spending and schedule plans.
Project steering group
See Steering group.
Project strategy
A comprehensive definition of how a project will be developed and managed.
Project success
The satisfaction of stakeholder needs measured by success criteria identified and agreed at project start.
Project success criteria
See Success criteria.
Project support experts
Individuals with expertise in particular aspects of project support.
Project support office
See Project office.
Project team
A set of individuals, groups, and/or organisations responsible to the project manager for working towards a common purpose.
Project variance
Changes to cost or schedule within the current work plan or scope.
Provider
A person or company providing goods or services.
Provider selection and management
The processes of identifying and selecting management providers through the project life cycle.
Punch list
A list of outstanding activities to be completed prior to final acceptance of deliverables.

Q

Qualitative risk analysis
A generic term for subjective methods of assessing risks that cannot be identified accurately.
Quality
The fitness for purpose or degree of conformance of outputs or processes to requirements.
Quality Assurance (QA)
The process of evaluating overall project performance regularly to provide confidence that quality standards will be satisfied.
Quality assurance plan
A plan guaranteeing a quality approach and conformance to all customer requirements for all project activities.
Quality audit
An official examination to determine whether practices conform to specified standards.
Quality control
Inspection, measurement, and testing to verify that project outputs meet acceptance criteria.
Quality criteria
The characteristics of a product determining whether it meets requirements.
Quality guide
Describes quality and configuration management procedures for people involved with quality reviews and technical exceptions.
Quality management
A discipline for ensuring outputs, benefits, and processes meet stakeholder requirements and are fit for purpose.
Quality management system
The complete set of quality standards, procedures, and responsibilities for a site or organisation.
Quality planning
Takes the defined scope and specifies acceptance criteria used to validate that outputs are fit for purpose.
Quality review
A review of a product against an established set of quality criteria.
Quantitative risk analysis
The estimation of numerical values of risk probability and impact on a project.

R

Rapid Application Development (RAD)
A method of minimising time necessary to complete development projects.
Reactive risk response
An action taken after a risk event has occurred.
Recurring costs
Expenditures against specific activities occurring on a repetitive basis.
Reduce
A response to a threat that reduces its probability, impact, or both.
Regulatory
A restriction due to the need to conform to a regulation or rule.
Reimbursement
Method by which a contractor will be paid for work undertaken.
Reject
A response to an opportunity where no action is taken.
Relationship
A logical connection between two activities.
Remaining duration
The time needed to complete the remainder of an activity or project.
Repeatable
The second level of a typical maturity model where basic processes are established.
Replanning
Actions performed for remaining effort within project scope.
Replenishable resource
A resource that can be restocked when depleted, such as raw materials or money.
Reporting
The formal communication of project information to stakeholders.
Request For Change (RFC)
A proposal for a change to the project.
Request For Proposal (RFP)
A bid document used to request proposals from prospective sellers of products or services.
Request For Quotation (RFQ)
Equivalent to a request for proposal but with more specific application areas.
Requirements
The stakeholders’ wants and needs clearly defined with acceptance criteria.
Requirements definition
A process ensuring the project includes all required work and then defines that work.
Requirements management
The process of capturing, assessing, and justifying stakeholders’ wants and needs.
Reserve
A planned allotment of time, cost, or other resources for unforeseeable elements within a project.
Residual value
The written-down value of a capital item at the end of the period.
Resource allocation
The process of attributing labour and non-labour resources to activities.
Resource availability
The level of availability of a resource, which may vary over time.
Resource calendar
A calendar defining working and non-working patterns for specific resources.
Resource-driven activity durations
Activity durations driven by the need for scarce resources.
Resource histogram
A view of project data showing resource requirements, usage, and availability using vertical bars against a horizontal timescale.
Resource level
A specified level of resource units required by an activity per time unit.
Resource levelling
An approach used during resource optimisation that delays activities to keep resource usage below specified limits.
Resource loading
The number of resources devoted to a specific activity in a particular time period.
Resource management
The acquisition and deployment of internal and external resources required for project delivery.
Resource optimisation
Methods for ensuring labour and non-labour resources are matched to the schedule.
Resource plan
A part of the project management plan stating how the project will be resource loaded and what supporting services are required.
Resource planning
A process evaluating what resources are needed to complete a project and determining the quantity needed.
Resource pool
The available resources to a project or a group of people who can generally do the same work.
Resource requirement
The requirement for a particular resource by a particular activity.
Resource scheduling
A process ensuring resources are available when needed and not underutilised where possible.
Resource smoothing
An approach used to utilise float or adjust resource requirements to smooth out peaks and troughs of resource usage.
Resources
All labour and non-labour items required to undertake the scope of work to the required quality.
Responsibility assignment matrix
A diagram or chart showing assigned responsibilities for elements of work.
Responsible organisation
A defined unit within the organisation structure assigned responsibility for accomplishing specific activities or cost accounts.
Retention
A part of payment withheld until the project is completed to ensure satisfactory performance.
Return on investment (ROI)
An expression of the value of an investment in change based on the gain in benefit relative to the cost.
Re-usable resource
A resource that becomes available for other uses when no longer needed.
Reviews
Project reviews take place throughout the project life cycle to check likely or actual achievement of specified objectives.
Re-work
Repeating work already completed to remove defects and meet acceptance criteria.
Right first time
Completing a deliverable which, on first testing, meets agreed acceptance criteria with no defects and no re-work required.
Risk
The potential of a situation or event to impact on the achievement of specific objectives.
Risk analysis
An assessment and synthesis of estimating uncertainty and/or specific risk events to understand their significance.
Risk analysis and management
A process allowing individual risk events and overall risk to be understood and managed proactively.
Risk appetite
How much risk investors are willing to tolerate in achieving their objectives.
Risk assessment
The process of quantifying the likelihood of risks occurring and assessing their likely impact on the project.
Risk attitude
The perception-driven choice of a person or group about an individual risk or overall project riskiness.
Risk avoidance
See Avoid (a threat).
Risk Breakdown Structure (RBS)
A hierarchical breakdown of the risks on a project.
Risk budget
A sum of money that is part of overall cost contingency to cover the cost impact of identified risks.
Risk context
The institutional and individual environment affecting how risk arises and should be managed.
Risk efficiency
The principle of risk-taking to achieve the minimum level of exposure for a given level of expected return.
Risk event
An uncertain event or set of circumstances that would, if it occurred, have an effect on the achievement of objectives.
Risk exposure
The degree to which a risk taker could be affected by an adverse outcome.
Risk identification
The capture of threats and opportunities to the project objectives.
Risk log
A document providing identification, estimation, impact evaluation, and countermeasures for all project risks.
Risk management maturity
A measure of the extent to which a project or organisation formally applies effective risk management.
Risk management plan
A document defining how risk management is to be implemented in the context of a particular project.
Risk manager
The person in charge of matters connected with risk on a project.
Risk monitoring
The process of observing the state of identified risks (also referred to as risk tracking).
Risk owner
The individual or group best placed to assess and manage a risk.
Risk prioritising
Ordering of risks according to their risk value and which need to be considered for reduction, avoidance, and transfer.
Risk ranking
The allocation of a classification to the probability and impact of a risk.
Risk reduction
Action taken to reduce the likelihood and impact of a risk.
Risk register
A document listing identified risk events and corresponding planned responses.
Risk response
An action or set of actions to reduce the probability or impact of a threat, or increase the probability or impact of an opportunity.
Risk response planning
The planning of responses to risks.
Risk techniques
Used to identify, assess, and plan responses to individual risks and overall risk.
Roll out
The process of delivering nearly identical products to multiple users, usually after testing.
Rolling wave planning
The process of planning short-term work in detail and longer-term work in outline only.

S

S-curve
A graphic display of cumulative costs, labour hours, or other quantities, plotted against time.
Safety plan
The standards and methods that minimise to an acceptable level the likelihood of accident or damage.
Sales
A marketing technique used to promote a project.
Sanction
Authorisation for the project or part of a project to proceed.
Scenario planning
A method used to anticipate potential future scenarios, useful in preparing to deal with emergent change.
Schedule
A timetable showing forecast start and finish dates for activities or events within a project.
Schedule dates
Start and finish dates calculated with regard to resource or external constraints as well as project logic.
Schedule Performance Index (SPI)
The ratio of work accomplished versus work planned, for a specified time period.
Schedule variance
The difference between the earned value and the planned value at any point in time.
Scheduled finish
The earliest date on which an activity can finish, considering resource or external constraints and project logic.
Scheduled start
The earliest date on which an activity can start, considering resource or external constraints and project logic.
Scheduling
The process used to determine overall project duration, including identification of activities, logical dependencies, and estimating durations.
Scope
The totality of outputs, outcomes, and benefits and the work required to produce them.
Scope change
Any change in project scope requiring a change in cost or schedule.
Scope creep
The continual extension of the scope of some projects.
Scope management
The process whereby outputs, outcomes, and benefits are identified, defined, and controlled.
Scope of work
A description of the work to be accomplished or resources to be supplied.
Scope statement
A documented description of the project identifying boundaries, output, approach, and content.
Scope verification
A process ensuring all identified project deliverables have been completed satisfactorily.
Secondary risk
The risk that may occur as a result of invoking a risk response or fallback plan.
Sensitivity analysis
An investigation of the effect on the outcome of changing parameters or data in procedures or models.
Sequence
The order in which activities will occur with respect to one another.
Setting
The relationship of the project, programme, or portfolio with its host organisation.
Share
A risk management response to an opportunity that increases its probability, impact, or both by sharing with a third party.
Simulation
A process whereby some dynamic aspect of a system is replicated without using the real system.
Six sigma
A quality management programme to achieve ‘six sigma’ levels of quality.
Slack
An alternative term for float. See Free float and Total float.
Slip chart
A pictorial representation of predicted completion dates of milestones (also referred to as a trend chart).
Slippage
The amount of float time used up by the current activity due to a delayed start or increased duration.
Snagging
The process of identifying minor small deficiencies that have to be rectified before acceptance of work.
Social capital
The pattern and intensity of networks among people and shared values arising from those networks.
Social system
The network of relationships between people involved in the project and how influences between actors work as a whole.
Sole source
The only source known to be able to supply particular equipment or services, or undertake a particular contract.
Solicitation
The process by which bids or tenders are obtained for the provision of goods or services.
Source selection
Choosing from potential contractors.
Spiral model
A management model used particularly for development projects.
Sponsor
A critical role as part of the governance board, accountable for ensuring work is governed effectively and delivers objectives meeting identified needs.
Sprint
A regular repeatable work cycle in agile development, typically a few weeks long.
Stage
A subdivision of the development phase created to facilitate approval gates at suitable points in the life cycle.
Stage payment
A payment made part-way through a project on completion of a pre-determined milestone.
Stakeholder
Individuals or groups who have an interest or role in the project or are impacted by it.
Stakeholder analysis
The identification of stakeholder groups, their interest levels, and ability to influence the project.
Stakeholder engagement
The systematic identification, analysis, planning, and implementation of actions designed to influence stakeholders.
Stakeholder grid
A matrix used to identify the relative importance of stakeholders to a project.
Stakeholder identification
The process of identifying stakeholders in a project.
Stakeholder management
See Stakeholder engagement.
Starting activity
An activity with no predecessors that does not have to wait for any other activity to start.
Start-to-finish
A dependency indicating that one activity cannot finish until another activity has started.
Start-to-start
A dependency indicating that one activity cannot start until another activity has started.
Start-to-start lag
The minimum time that must pass between the start of one activity and the start of its successor(s).
Start-up
The formal process of making a new project team effective or commissioning a completed facility.
Start-up meeting
The initial meeting with the project team at the start of a project or phase.
Statement of scope
See Scope statement.
Statement of work
An annex to the main body of a contract defining the detail of deliverables, timescales, and management procedures.
Status report
A description of where the project currently stands, usually in the form of a written report.
Steering group
A group comprising the sponsor, senior managers, and sometimes key stakeholders, setting strategic direction for a project.
Story point
A method of estimating completion/forecasting work yet to complete on a user story in iterative life cycles.
Strategic intent
The aspirational plans, overarching purpose, or intended direction needed to reach an organisational vision.
Strategic management
The identification, selection, and implementation of an organisation’s long-term goals and objectives.
Strategic sourcing
An analysis of buying strengths and weaknesses enabling procurement strategies to maximise advantages and respond to supply disruption risks.
Strategy
The high-level plan enabling the project to reach a successful conclusion, describing how it is to be executed.
Subcontract
A contractual document legally transferring responsibility for providing goods, services, data, or hardware from one firm to another.
Subcontractor
An organisation that supplies goods or services to a supplier.
Subject matter experts
Users with subject matter knowledge and expertise who may contribute to defining requirements and acceptance criteria.
Subproject
A group of activities represented as a single activity in a higher level of the same project.
Success criteria
The satisfaction of stakeholder needs for the deployment of a project.
Success factors and maturity
Management practices that, when implemented, increase the likelihood of project success. The degree of establishment indicates organisational maturity.
Successor
An activity whose start or finish depends on the start or finish of a predecessor activity.
Sunk costs
Costs that are unavoidable, even if the remaining work is terminated.
Super-critical activity
An activity behind schedule with negative float.
Supplier
A contractor, consultant, or organisation that supplies resources to the project.
Supply chain management
The management of the chain of organisations through which goods pass from raw materials to the ultimate purchaser.
Surety
An individual or organisation agreeing to be legally liable for the debt, default, or failure of a principal to satisfy a contractual obligation.
Sustainability
An approach balancing environmental, social, economic, and administrative aspects to meet current stakeholder needs without compromising future generations.
SWOT (analysis)
A technique used to identify strengths, weaknesses, opportunities, and threats inherent in a project.
System
The complete technical output of the project including technical products.
Systems analysis
The analysis of a complex process or operation to improve its efficiency.
Systems engineering
A systematic approach to realising a project that takes account of all related systems and subsystems.
Systems management
Management including prime activities of systems analysis, design, engineering, and development.

T

Talent management
The ability to attract, motivate, and retain high-quality people to deliver strategic goals and objectives.
Target completion date
The date planned to complete an activity or project.
Target start date
The date planned to start work on an activity or the project.
Task
The smallest indivisible part of an activity when broken down to a level best understood and performed by a specific person or organisation.
Team
A group of people working in collaboration or cooperation towards a common goal.
Team building
The ability to gather the right people to join a project team and get them working together for project benefit.
Team development
The process of developing skills, as a group and individually, that enhance project performance.
Team leader
The person responsible for leading a team.
Team member
A person accountable to and with work assigned by the project manager.
Teamwork
A group of people working in collaboration or cooperation towards a common goal.
Technology management
The management of the relationship between available and emerging technologies, the organisation, and the project.
Temporary organisation
A specific project, programme, or portfolio team brought together to implement project-based work.
Tender
A document proposing to meet a specification in a certain way and at a stated price.
Tender document
The document issued to prospective suppliers when inviting bids or quotations.
Tender list
A list of approved suppliers to whom a specific enquiry may be sent.
Tendering
The process of preparing and submitting a tender, quotation, or bid.
Termination
The decommissioning and disposal of a deliverable at the end of its useful life.
Terms and conditions
All the clauses in a contract.
Terms of reference
A specification of a team member’s responsibilities and authorities within the project.
Testing
The process of determining how aspects of a deliverable perform when subjected to specified conditions.
Theory of constraints
A theory expounded by Goldratt, leading to the critical chain schedule management technique.
Threat
A negative risk event that, if it occurs, will have a detrimental effect on objectives.
Three-point estimate
An estimate giving optimistic best case, pessimistic worst case, and most likely values.
Time analysis
The process of calculating early and late dates for each activity based on duration and logical relations.
Time recording
The recording of effort expended on each activity to update a project plan.
Time scheduling
Techniques used to develop and present schedules showing when work will be performed.
Time sheet
A means of recording actual effort expended against project and non-project activities.
Time variance
The scheduled time for work to be completed less the actual time.
Timebox
A fixed unit of time during which work is performed, typically used in iterative approaches.
Time-driven
Control actions or reports triggered by the passage of a defined interval.
Tolerance
A level of delegated permission to vary performance from specified parameters.
Top down cost estimating
Estimating total project cost based on historical costs and other variables, then subdividing to individual activities.
Total float
Time by which an activity may be delayed or extended without affecting overall duration or violating a target finish date.
Total Quality Management (TQM)
A strategic, integrated management system for customer satisfaction guiding all employees in every aspect of their work.
Traffic light reports
A type of progress report explaining current status using traffic light colours.
Tranche
A subdivision of the deployment phase of a programme designed to enable an incremental approach to development.
Transfer
A response to a threat that reduces its probability, impact, or both by transferring to a third party.
Transition
The fourth phase in a linear cycle where results are handed over, commissioned, and accepted by the sponsor.
Trend chart
See Slip chart.
Trends
A general tendency observed on a project.
Triple constraint
A way of describing the fundamental trade-off between time, cost, and quality in delivering project scope.
Turnaround report
A report created for managers to enter progress status against activities scheduled to be in progress during a particular time window.
Turnkey contract
A comprehensive contract where the contractor is responsible for complete supply of a facility.

U

Uncertain event
See Risk event.
Uncertainty
A state of incomplete knowledge about a proposition, usually associated with risks.
User acceptance test
A formal test demonstrating the acceptability of a product to the user.
User requirements
Requirements governing project deliverables as expressed by the user.
User requirements statement
A document defining user needs from the user’s perspective.
User story
An informal, simple language description of system features, often written from an end user’s perspective.
Users
The group of people intended to work with deliverables to enable beneficial change.

V

V life cycle
A graphical representation of a life cycle where horizontal lines connect related front and backend phases.
Validate
Testing that the deliverable meets requirements.
Validation
The process of providing evidence that a deliverable meets user needs.
Valuation
A calculation of payment due under contract terms, often undertaken at stages in large contracts.
Value
A standard, principle, or quality considered worthwhile or desirable.
Value engineering
Concerned with optimising conceptual, technical, and operational aspects of deliverables.
Value for money ratio
The ratio of monetary and non-monetary benefits to the investment of resources committed.
Value management
A structured approach to defining what value means to the organisation and reviewing whether it can be improved.
Value tree
A graphical representation of the relationship between different factors driving value.
Variable or recurring cost
A cost influenced by volume of business or quantity, such as a recurring operational cost.
Variation
A change in scope or timing of work that a supplier is obliged to do under a contract.
Variation order
The document authorising an approved technical change or variation.
Vendor
A company or person contractually committed to provide goods (either direct or through a supplier).
Verification
Proof of compliance with specified requirements, determined by test, analysis, inspection, or demonstration.
Verify
Testing that the deliverable meets the specification and designs.
Version control
The recording and management of different versions of the project’s products.
Virtual models
A visual representation of a deliverable, used to test its operational performance.
Virtual team
A team where people are separated by geography and potentially time zone.
Vision statement
An outward-facing description of new capabilities resulting from project or programme delivery.
VUCA conditions
A phrase describing an organisational context with inherent uncertainty, standing for volatility, uncertainty, complexity, and ambiguity.

W

Warranty
A promise given by a contractor regarding the nature, usefulness, or condition of supplies or services delivered.
Waterfall method
A type of life cycle where phases are sequential. See Linear life cycle.
Weighted Average Cost of Capital (WACC)
The minimum average return an organisation must earn on existing assets to satisfy capital providers.
What-if assessment
The process of evaluating alternative strategies.
What-if simulation
A technique evaluating the impact of scope, schedule, or methodology changes on contract dates or baseline schedule.
Whole-life costs
The fixed and variable capital and operational costs required to develop, use, and terminate a product or asset.
Work
The total number of hours, people, or effort required to complete an activity.
Work breakdown code
A code representing the ‘family tree’ of an element in a work breakdown structure.
Work Breakdown Structure (WBS)
Defines the total work to be undertaken and provides a structure for all control systems.
Work load
The amount of work units assigned to a resource over a period of time.
Work package
A discrete element of project scope at the lowest level of each branch of the work breakdown structure.
Work package manager
A person responsible for leading and managing part of a project to achieve specific aims agreed with the project manager.
Work units
Units providing measurement for resources, such as labour hours for people.
Working group
A group of two or more people to which work is delegated and interrelationships between activities are managed through a single person.
Workplace stress
The adverse reaction people have to excessive pressure or other types of demand placed upon them.

X

X-Bar control charts
Charts displaying means and sample ranges for periodically gathered, same-size samples of product or process characteristics.

Y

Yield
The return on an investment.

Z

Zero defects
A measure of quality where the deliverable is defect-free.
Zero float
A condition where there is no excess time between activities. An activity with zero float is considered critical.

This website use cookies.